Mr. Anderson, a logistics manager, is overseeing a major project to streamline the supply chain operations of his company. During the implementation phase, unexpected delays occur due to issues with a critical supplier. What proactive steps should Mr. Anderson take to mitigate the impact on project timelines and maintain stakeholder confidence?